This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews began the installation of concrete beam and deck forms for the second section of the fourth-floor concrete deck. The installation of the reinforcing steel and post tensioning cables for the first section of the fourth-floor concrete deck was completed this past week.

Maui Kupono crews grading Market Street entrance roadway  
HDCC and CMC crews setting formwork and reinforcing steel for the parking structure foundation at Church Street 
CMC crews completing the installation of reinforcing steel and post tensioning cables for the fourth-floor concrete deck
HDCC crews setting beam and deck forms for the fourth-floor concrete deck

Vineyard Street Improvements:
The MIRA crews completed the drainage system improvements this week and will commence with the underground electrical and communication infrastructure work next week.

Mira crews backfilling new drain inlet structure on Vineyard Street
Mira crews installing concrete drainage structure on Vineyard Street
Mira crews excavating for new drainline on Vineyard Street

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway, Wells Park and War Memorial Stadium Parking Lot) and various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, click here.