Wailuku construction update

This week’s construction update

Wailuku Parking Structure:

The Hawaiian Dredging crews poured the second section of the parking structures second-floor concrete deck this week. The HDCC and CMC crews also continued work on the second floor concrete columns and walls.   

HDCC crews pouring the parking structures second floor concrete deck
HDCC crews removing the second floor beam formwork
HDCC and CMC crews installing reinforcing steel for the second floor concrete columns

Vineyard Street Improvements:

The MIRA crews continued with the installation of the sewer system improvements on Vineyard Street between Church and High Street this past week. The Hawaiian Electric, MIRA and Wasa Electric crews also converted the existing overhead electrical service to the Weinberg Building on Lower Vineyard Street to underground this past week.  MIRA crews installing new sewer system laterals

MIRA crews installing new sewer system laterals
Hawaiian Electric, MIRA and Wasa Electric crews converting the electrical service from overhead to underground at the Weinberg Building

General Notices:

Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm. 

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway, Wells Park and War Memorial Stadium Parking Lot) and various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please visit www.wailukulive.com.