This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews continued with the installation of post tensioning cables and reinforcing steel for the second floor of the third section of the parking structure which will be poured next week. Hawaiian Dredging crews also commenced with the setting of concrete beam and deck forms for second floor of the fourth section of the parking structure this week.

Hawaiian Dredging crews setting the second-floor concrete deck form
Hawaiian Dredging and CMC crews installing reinforcing steel for the second-floor concrete deck
Southeast corner of the parking structure

Vineyard Street Improvements:
The MIRA crews continued with the concrete curbing work for the street this week. Wasa Electric also commenced with the installation of the new streetlights.

New streetlight fixtures
MIRA crews pouring concrete curbs

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.