LATEST UPDATES

This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews commenced with the installation of post tensioning cables and reinforcing steel for the for the second floor of the fourth section of the parking structure this week. The HDCC and CMC crews are also continuing work on the second-floor concrete columns and walls.

Hawaiian Dredging crews installing column and wall forms at the second floor
Hawaiian Dredging and CMC crews installing post tensioning cables and reinforcing steel for the second-floor concrete deck

Vineyard Street Improvements:
The MIRA crews continued with the concrete curbing work for the street this week.

MIRA crews installing concrete curbs on Vineyard Street

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.