This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews commenced with the installation of post tension cables and reinforcing steel for the third section of the third- floor concrete deck. The Hawaiian Dredging crews also began setting the third-floor concrete beam and deck formwork for the fourth section of the parking structure.

CMC crews installing post tensioning cables and reinforcing steel for the third floor
HDCC crews setting concrete beam forms for the third floor
HDCC crews pouring concrete for the new sidewalk access from Main Street
Aerial photo of the project

Vineyard Street Improvements:
The MIRA crews continued with the concrete curbing and sidewalk work for the street this week.

MIRA crews excavating for concrete curbs
Setting concrete curb forms
MIRA crews setting concrete curb forms and pouring concrete curbs

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.