This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews also completed the installation of post tension cables and reinforcing steel for the fourth section of the third-floor concrete deck of the parking structure this week. The Hawaiian Dredging crews also commenced with the installation of the third-floor concrete columns and walls for the third section of the parking structure.

CMC crews completing reinforcing steel installation for the third-floor concrete deck
Hawaiian Dredging crews working on third-floor concrete columns and walls
Maui Kupono crews installing aggregate basecourse at the First Hawaiian Bank parking lot

Vineyard Street Improvements:
The MIRA crews continued with the concrete curbing, sidewalk and driveway work for the street this week.

MIRA crews demolishing existing sidewalks
MIRA crews preparing and pouring new concrete driveway entrances

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.