This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews completed the installation of post tension cables and reinforcing steel for the third section of the third- floor concrete deck. The concrete deck will be poured next week Monday. The Hawaiian Dredging crews also completed setting the third-floor concrete beam and deck formwork for the fourth section of the parking structure.

Hawaiian Dredging crews pouring concrete ramp
Hawaiian Dredging crews setting concrete deck forms for the fourth section of parking structure
CMC crews completing the installation of post tension cables and reinforcing steel for the third floor concrete deck
Maui Kupono crews placing and compacting aggregate basecourse for the access roadway

Vineyard Street Improvements:
The MIRA crews continued with the concrete curbing, sidewalk and driveway work for the street this week.

MIRA crews grading for driveway and sidewalk
MIRA crews setting concrete curb forms
MIRA crews pouring concrete driveway

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.