This week’s construction update

Wailuku Parking Structure:
The HDCC crews continued with work on the entrance structure at Church Street. Fire sprinkler, plumbing, electrical and painting work within the parking structure is also continuing.

HDCC crews working on entrance structure concrete walls
HDCC crews working on entrance structure concrete walls
HDCC subcontractor crews working on interior of parking structure

Vineyard Street Improvements:
The MIRA crews completed the preparation of the roadway pavement structure for asphalt paving this week. The asphalt paving for both Vineyard and Church Streets shall commence next week.

MIRA crews preparing Vineyard Street for paving
MIRA crews preparing Vineyard Street for paving

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.