This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews commenced with the installation of reinforcing steel and post tensioning cables for the second section of the fourth-floor concrete deck. The Maui Kupono crews also began preparatory work for the third section of parking structure ground floor concrete slab this week.

Maui Kupono crews excavating and grading site for the ground floor concrete pavement
CMC crews installing reinforcing steel and post tensioning cables for the fourth-floor concrete deck
HDCC crews cleaning second-floor concrete deck
HDCC crews setting concrete wall forms at the parking structure entrance at Church Street

Vineyard Street Improvements:
The MIRA and Wasa Electric crews continued with the installation of the underground electrical and communication infrastructure work this week.

Mira and Wasa crews installing electrical concrete manhole structure
Wasa Electric crews installing underground electrical and communication ductlines

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, click here.