This week’s construction update

Wailuku Parking Structure:
The CMC crews also completed the installation of post tension cables and reinforcing steel for the fourth section of the top floor concrete deck which will be poured next week. Painting work for the parking structure also commenced this week.

CMC crews completing the installation of post tension cables and reinforcing steel for the fourth-floor concrete deck
HDCC crews setting forms for concrete stairs
JD Painting crews commencing with painting work

Vineyard Street Improvements:
The MIRA crews continued with the concrete curb and sidewalk work for the street this week. The Wasa Electric crews also continued with the installation of the last section of underground electrical and communication conduits this past week.

MIRA setting forms for concrete curbs at the Vineyard Street
MIRA crews grading for new sidewalks

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.