This week’s construction update

Wailuku Parking Structure:
The HDCC and Maui Kupono crews continued with work on the entrance structure at Church Street. The Maui Kupono crews also continued with the asphalt paving of the access roadway from Market Street.

HDCC crews pouring the concrete entrance ramp to the parking structure
HDCC crews pouring concrete wall at the entrance structure
HDCC crews pouring concrete ramp to the top floor of the parking structure
Maui Kupono crews paving First Hawaiian Bank parking lot and access roadway

Vineyard Street Improvements:
The MIRA crews continued with the concrete sidewalk and driveway apron work for the street this week. The MIRA and County DWS crews also removed the old fire hydrant connections.

MIRA crews pouring new concrete driveway
MIRA crews excavating and grading for new concrete crosswalk
MIRA crews disconnecting and removing old fire hydrant laterals

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.