LATEST UPDATES

This week’s construction update

Wailuku Parking Structure:
The HDCC crews continued with work on the entrance structure at Church Street. Fire sprinkler, plumbing, electrical and painting work within the parking structure is also continuing.

HDCC crews working on Church Street entrance structure
HDCC subcontractor crews working on the interior of the parking structure
HDCC crews working on concrete ramps walls within the structure

Vineyard Street Improvements:
The MIRA crews continued with the roadway pavement reconstruction work this past week.

MIRA crews removing the existing pavement structure and placing aggregate basecourse on Vineyard Street
MIRA crews fine grading aggregate basecourse on Vineyard Street

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.