Wailuku Parking Structure:
The Hawaiian Dredging crews continued with the setting of the fourth-floor concrete beam and deck formwork for the fourth section of the parking structure this week. The Hawaiian Dredging and CMC crews also completed the installation of the post tension cables and reinforcing steel for the third section of the fourth-floor concrete deck.

HDCC crews setting concrete beam and deck formwork for the fourth floor
CMC crews completing the installation of post tension cables and reinforcing steel for the fourth-floor concrete deck
HDCC crews pouring concrete walls for the parking structure entrance

Vineyard Street Improvements:
The MIRA crews continued with the concrete curb and sidewalk work for the street this week.

MIRA setting forms for concrete curbs at the Vineyard and High Street intersection
MIRA crews pouring concrete curbs

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.