This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging crews commenced with the setting of the fourth-floor concrete beam and deck formwork for the fourth section of the parking structure this week. The Hawaiian Dredging and CMC crews also began installing post tension cables and reinforcing steel for the third section of the fourth-floor concrete deck.

HDCC crews setting concrete beam and deck formwork for the fourth floor
CMC crews installing post tension cables and reinforcing steel for fourth-floor concrete deck
HDCC crews working on concrete walls for the parking lot entrance structure
Maui Kupono crews working on the new access driveway

Vineyard Street Improvements:
The MIRA crews continued with the concrete sidewalk and driveway work for the street this week.

MIRA crews working on concrete sidewalks
MIRA crews pouring concrete driveway
MIRA crews excavating for concrete curbs at the Vineyard and High Street intersection

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.