This week’s construction update

Wailuku Parking Structure:
The Hawaiian Dredging and CMC crews poured the second section of the fourth-floor concrete deck this week. The Maui Kupono crews continued with the preparatory work for the third and fourth sections of the parking structure ground floor concrete slab this week.

CMC crews installing reinforcing steel for the parking structure foundation
HDCC crews pouring concrete for the fourth-floor deck

Vineyard Street Improvements:
The MIRA and Wasa Electric crews continued with the installation of the underground electrical and communication infrastructure work this week.

Mira crews backfilling electrical and communication trenches
Mira crews excavating trench for electrical and communication ductlines
Wasa Electric crews installing electrical and communication ductlines
Hawaiian Telcom crews installing new fiber communication lines at Church Street

General Notices:
Due to the ongoing work on Vineyard Street, motorists and pedestrians should be cautious when traversing through the area. Vineyard Street between Church and High Street will be closed to thru traffic Monday to Friday between the hours of 8:30 am to 3:30 pm.  

The Wailuku Parking lot is completely closed. Parking is available in various locations, as well as free shuttle service on Da Bee (includes parking at Maui Lani Safeway and Wells Park with various “flower” stops in Wailuku. For information on shuttle schedules/routes and a list of parking locations in Wailuku, please click here.