Construction continues to progress at the Hālau of ʻŌiwi Artsite. This week, crews began work on tilt-up panels while advancing structural rebar installation and rough-ins for plumbing and electrical systems. Multiple trades are actively coordinating to keep foundational work moving forward.
Pictured above: F&H crews installing formwork for tilt-up panels.