HOA Maui Construction Update – Week Ending January 16, 2026

This week’s construction update highlights continued site preparation at the Hālau of ʻŌiwi Art site, with crews focused on grading, drainage installation, and slab edge formwork in preparation for the precast casting slabs.

Toms Backhoe crew grading and backfilling for precast casting slab.

Toms Backhoe crew installing 13” drain lines.

F&H Crews laying out and installing slab edge forms at the precast casting slabs.

Site photo.