Construction continues on the new Hālau of ʻŌiwi Art (HOA Maui) at Vineyard Street and North Church Street in Wailuku. This week, crews focused on backfilling and compaction, rebar installation, concrete pouring, and formwork for the future pedestrian bridge connecting the facility to the Wailuku Parking Garage. You can also follow construction activities through the live video feed at www.wailukulive.com/hoa.
General Notices
Construction on HOA Maui began on April 28, 2025, and is scheduled for completion by April 19, 2027, subject to change. Please expect typical commercial construction noise during this period. For questions, contact F&H Construction Superintendent Terry at 808-495-7952.
Pictured above: CMC crews installed rebar on Level 2 above the loading dock.