HOA Construction Update – May 15, 2026

Work at the Hālau of ʻŌiwi Arts continued to show steady progress this week, with crews focusing on the project’s tilt-up panel construction. Activities included rebar installation, electrical rough-in, formwork preparation, and another panel pour completed on May 13 (pictured above).

CMC Crews installing rebar in panels.

Alakai Electric roughing in electrical at panels.

F&H and Reef Development pouring tilt-up panels.

Reef Development and F&H crews installing formwork for tilt-up panels.

Site photo of tilt-up panels poured on May 13, 2026.