This week’s work at Hālau of ʻŌiwi Art in Wailuku included metal decking installation, concrete pours, layout work for the showers and storage area, and backfill and compaction between the Hālau and Wailuku parking garage.

Pictured above: F&H crews pour concrete walls and columns at Retail 1.

Dorvin D. Leis and Alaka‘i Electric crews complete layout work at Level 1B for the future showers and storage area.

Tom’s Backhoe crews backfill and compact the area between Hālau of ʻŌiwi Art and the Wailuku parking garage.

Certified Welders crews install metal decking at Level 1B.